Assembly Cost Estimation
Post Reply   Forum
Posted by: Techian ®

06/18/2003, 07:50:39

Author Profile Mail author Edit

1)Is there a Standard Process in Estimating the cost to assemble a Cover Transmission Chain Assembly?
This is an Assembly composed of 10 different parts.
The quantity is low, hence Automation is ruled out.
No sample Part Available. Only Blue print available.

2) What is the best way to estimate (Cycle Time+Set Up Time) an Assembly using Manual Labor and simple fixtures?

3)Any Suggestions/recommendations to Estimate Assembly Process.

Thank You,
Techian







Post Reply | Recommend | Alert Rate View All   Previous | Next |

Replies to this message


Re: Assembly Cost Estimation
Re: Assembly Cost Estimation -- Techian Post Reply Top of thread Forum
Posted by: prop154 ®

07/02/2003, 07:13:37

Author Profile Mail author Edit

You will need to know how many shifts and operators required to meet production, along with any conusmables you may need.

2) I would suggest using a celluar set-up and incorporate flexable manpower (example set up the process with four people producing 10 units per day. then if needed you can drop your staffing to 2 people at 5 units per day). Also make sure you get accurate cycle times you will need to establish a good takt-time in order to eliminate non-value added movements

 

Hope this helps.







Post Reply | Recommend | Alert Rate Where am I? Original Top of thread Previous |   |
assy est methods
Re: Assembly Cost Estimation -- Techian Post Reply Top of thread Forum
Posted by: RKimball ®

06/18/2003, 23:21:18

Author Profile Mail author Edit
Techian,
Sorry, but the best way I have ever found is to have enough experience and knowledge of the job to be able to faithfully act out the process from start to finish at your desk with a watch ticking. If this is a lengthly process you can mentally divide it into what you consider equal parts then time one part and multiply by the number of parts. Accuracy is dependant on your ability to act out and prorate the additional processes in. This is a skill!

good luck
-randy-




** The worst suggestion of your lifetime may be the catalyst to the grandest idea of the century, don't fail to listen to suggestions. -randy-


Post Reply | Recommend | Alert Rate Where am I? Original Top of thread Previous | |

Powered by Engineers Edge

© Copyright 2000 - 2024, by Engineers Edge, LLC All rights reserved.  Disclaimer